13 March 2008 - Day 5
< Prev Next >

Not a lot of visual progress today. In fact it seems like I should have gotten more done. Plumbing is all done and tested. Electrical is all done. I will put up the green board tomorrow, although it was supposed to get done today.

The big advance was getting to the tile today. You can see that below.

Even thought it looks almost like last night, Everything is glued, shower poles are in, anything can be hit with a Mack truck and will not move (I have shower heads that have play) and it was pressure tested for six hours.

The dark green will be the bottom 3 feet and the white will be the top three feet. Besides being on the floor, a band two tiles wide of the floor tile will separate the top and bottom.

A view from a little further back.