Not a lot of visual progress today. In fact it seems like I should have gotten more done. Plumbing is all done and tested. Electrical is all done. I will put up the green board tomorrow, although it was supposed to get done today. The big advance was getting to the tile today. You can see that below. | |
![]() |
Even thought it looks almost like last night, Everything is glued, shower poles are in, anything can be hit with a Mack truck and will not move (I have shower heads that have play) and it was pressure tested for six hours. |
![]() |
The dark green will be the bottom 3 feet and the white will be the top three feet. Besides being on the floor, a band two tiles wide of the floor tile will separate the top and bottom. |
![]() |
A view from a little further back. |